Q149211 Inglês
          One frequently overlooked area in planning is technical reviews and inspections. A technical review requires substantial preparation on the part of the presenters. Documents must be published and distributed and presentation material organized and made into slides or overheads. Practice sessions are conducted by presenters with an audience of critics to prepare for the review.
              The reviewers should read the material, attend the presentations, and write reports. On large projects with many reviews and walk-throughs involving many participants, a substantial number of labor hours can be consumed analyzing documents, attending meetings, and writing reports. For example, a system design review for one module or unit can require 150 labor hours. When overlooked, this labor can result in a very large error in resource and schedule estimation.
          Many projects include risk assessment and risk management as a key part of the planning process and expect the plan to identify specific risk areas. The plan is expected to quantify both probability of failure and consequences of failure and to describe what will be done to contain development risk.
                                 A. Behforooz and F. Hudson. Software engineering fundamentals. Ed. Oxford (adapted).

Based on the text above, judge the following items.
At the beginning of the second paragraph, “should” can be correctly replaced by ought to.
Alternativas
Q149210 Inglês
          One frequently overlooked area in planning is technical reviews and inspections. A technical review requires substantial preparation on the part of the presenters. Documents must be published and distributed and presentation material organized and made into slides or overheads. Practice sessions are conducted by presenters with an audience of critics to prepare for the review.
              The reviewers should read the material, attend the presentations, and write reports. On large projects with many reviews and walk-throughs involving many participants, a substantial number of labor hours can be consumed analyzing documents, attending meetings, and writing reports. For example, a system design review for one module or unit can require 150 labor hours. When overlooked, this labor can result in a very large error in resource and schedule estimation.
          Many projects include risk assessment and risk management as a key part of the planning process and expect the plan to identify specific risk areas. The plan is expected to quantify both probability of failure and consequences of failure and to describe what will be done to contain development risk.
                                 A. Behforooz and F. Hudson. Software engineering fundamentals. Ed. Oxford (adapted).

Based on the text above, judge the following items.
The plan is supposed to include the likelihood of failure, its results and the actions to be taken to contain development risk.
Alternativas
Q149209 Inglês
          One frequently overlooked area in planning is technical reviews and inspections. A technical review requires substantial preparation on the part of the presenters. Documents must be published and distributed and presentation material organized and made into slides or overheads. Practice sessions are conducted by presenters with an audience of critics to prepare for the review.
              The reviewers should read the material, attend the presentations, and write reports. On large projects with many reviews and walk-throughs involving many participants, a substantial number of labor hours can be consumed analyzing documents, attending meetings, and writing reports. For example, a system design review for one module or unit can require 150 labor hours. When overlooked, this labor can result in a very large error in resource and schedule estimation.
          Many projects include risk assessment and risk management as a key part of the planning process and expect the plan to identify specific risk areas. The plan is expected to quantify both probability of failure and consequences of failure and to describe what will be done to contain development risk.
                                 A. Behforooz and F. Hudson. Software engineering fundamentals. Ed. Oxford (adapted).

Based on the text above, judge the following items.
In a lot of projects, it is hoped that the plan should be able to spot specific risky areas.
Alternativas
Q149207 Inglês
          One frequently overlooked area in planning is technical reviews and inspections. A technical review requires substantial preparation on the part of the presenters. Documents must be published and distributed and presentation material organized and made into slides or overheads. Practice sessions are conducted by presenters with an audience of critics to prepare for the review.
              The reviewers should read the material, attend the presentations, and write reports. On large projects with many reviews and walk-throughs involving many participants, a substantial number of labor hours can be consumed analyzing documents, attending meetings, and writing reports. For example, a system design review for one module or unit can require 150 labor hours. When overlooked, this labor can result in a very large error in resource and schedule estimation.
          Many projects include risk assessment and risk management as a key part of the planning process and expect the plan to identify specific risk areas. The plan is expected to quantify both probability of failure and consequences of failure and to describe what will be done to contain development risk.
                                 A. Behforooz and F. Hudson. Software engineering fundamentals. Ed. Oxford (adapted).

Based on the text above, judge the following items.
Large projects demand patient learning to go through it.
Alternativas
Q149206 Inglês
          One frequently overlooked area in planning is technical reviews and inspections. A technical review requires substantial preparation on the part of the presenters. Documents must be published and distributed and presentation material organized and made into slides or overheads. Practice sessions are conducted by presenters with an audience of critics to prepare for the review.
              The reviewers should read the material, attend the presentations, and write reports. On large projects with many reviews and walk-throughs involving many participants, a substantial number of labor hours can be consumed analyzing documents, attending meetings, and writing reports. For example, a system design review for one module or unit can require 150 labor hours. When overlooked, this labor can result in a very large error in resource and schedule estimation.
          Many projects include risk assessment and risk management as a key part of the planning process and expect the plan to identify specific risk areas. The plan is expected to quantify both probability of failure and consequences of failure and to describe what will be done to contain development risk.
                                 A. Behforooz and F. Hudson. Software engineering fundamentals. Ed. Oxford (adapted).

Based on the text above, judge the following items.
The reviewers must read and rewrite the material while being present in the meetings.
Alternativas
Respostas
1: C
2: C
3: E
4: C
5: E